Key Summary For SIT MOOAQRRelease05
 
Key Summary
Status
 
Date Comments Status
5/23/2005 AQR FY06 SIT Started today, Monday, May 23, 2005* SIT BVT Completed on Friday, May 20, 2005 * Code Dropped into SIT for K7, G3 & Z22 projects* Code Drop planned for Z18 on Tuesday, May 24, 2005 EOD IST Green
5/24/2005 Code will be dropped for Z18 Xbox Xenon tonight IST* Test is unable to execute G3 & SAP related RRM Regression Scripts due to Blocking Issue PS# 11542. Cindi is following up on this DCOM Issue with SAP Sales & Distribution DCOM Issues team. Green
5/25/2005 Code dropped for Z18 Xbox Xenon & completed BVT successfully * Blocking issue #11542 resolved today which was impacting G3 & RRM test script execution * Z22 ACER SCM B2B Integration - Received changed receiver key attribute for Acer (Acer HQ instead of Acer Incorporated). Test processed data to verify the event flow. Green
5/26/2005 Code dropped for Xbox Blocking PS Items & Other resolve PS Items today 7PM IST * Z22 ACER SCM B2B Integration - Blocking Issue PS# 11569 is resolved at 7PM IST and test execution is in progress* Blocking Issue PS # 11556 impacting OSRY functionality of RRM; Nilesh & Sreeram to follow-up with Redmond team today 5/26 PST* PS #11565 is impacting major Xenon functionality (16 test scripts); assigned to Shivani for follow-up* India Test team to work from 1:30 PM IST tomorrow Friday, May 27 due to power outage Green
5/27/2005 Code for Z26B TVMainOptimization will be dropped today at 9PM IST with other resolved PS Items; Test to start TVMain regression from Monday, May 30, 2005* Blocking PS Item # 11578 impacting 30 XBox test scripts; Currently assigned to Mike Adams for follow-up Yellow
5/30/2005 Code will be dropped tonight for Blocking PS Item # 11578 that is impacting major XBox functionality* Z26B-TV Main Optimization: Test Team started executing Test Scripts related to Retired TV Rules for COA; DTP preparation is in progress (Target date of completion 6/1)* Z16 Rebate Tracking - In ESG: As per dev, Code will be available at the end of SIT Test Pass 2 (6/9 or 6/10); Test has set up a meeting on tomorrow, 5/31 with PM to discuss on contingency plan* G3 Effective Dated Pricing: Blocking PS iteam # 11556 closed today; Test is making good progress on test script execution* Test is blocked with PS Item # 11590 impacting execution of DSS Direct Sales Out regression Test Scripts; RSA is working on the resolution* The status is yellow as Z26B TV Main Optimization, Z26C RMA CR and Z16 Rebate Tracking - In ESG are being dropped late into SIT & Z18 XBOX Platform is being blocked by PS Item # 11578 Yellow
5/31/2005 PS #11594 is blocking entire TVMain functionality – 200 test scripts (Z26B is blocked completely); Currently resolved and needs a code drop* PS #11596 is blocking entire Xbox Order Invoicing functionality (53 Test Scripts); Currently resolved and needs a code drop* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT; Z26B TV Main Optimization and Z18 XBOX Platform are being blocked Yellow
6/1/2005 SIT Test Pass 1 completed today; Test Pass 2 will start tomorrow Thursday, June 02, 2005 as planned* Z26B TV Main Optimization - Test Pass 1 to continue through this week * PS #11609 is Blocking the execution of 53 Test Scripts related to XBox and 200 Test Scripts related to TV Rules for COA; Resolved by RSA at 8:00 PM today * The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT; Z26B TV Main Optimization and Z18 XBOX Platform are being blocked Yellow
6/2/2005 Test Pass 2 started today Thursday, June 02, 2005 as planned* G3 NonSAP Effect Dated Pricing - Two CRs (PS #11605 & #11613) will be dropped tonight * Blocking PS item # 11615 impacted E2E script execution for 4 hours; Issue was resolved at 6:30PM IST* Blocking PS item # 11597 is impacting Scrap Tracking Report Test Scripts; Dev is investigating on this* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT Yellow
6/3/2005 Test Pass 2 In Progress* Z18 XBOX Platform: Test team could not complete In Progress test cases due to blocking PS#11621. This will be dropped tonight IST drop.* Z22 Acer SCM B2B Integration: As per the discussion with PM, test team will try to test the flow of 9Z9 process. PM is working with the Ebis, RSA and Dev to find out the issue that is blocking the 9Z9 processing. As per the PM: "we will try working on this issue until 6/10 to resolve itself, if not resolved by 6/10 then we will look at pulling the 9z9 process from testing."* G3 NonSAP Effect Dated Pricing: 7 Test cases are blocked because of PS#11539 (Data not flowing from SAP to feedstore & RRMDB). * Z26B TV Main Optimization: Test team was impacted due to PS# 11609 (Events pumped were not moving from EventStage table because job ArchiveData which has blocked many processes on COADB); Test has received the review comments from PM on the DTP. DTP modification and Test case preparation in progress as per the review comments. Test will send DTP & Test Scripts to PM (Yukako) by EOD today for review/sign off.* AQR Regression: Blocking PS item #11539 (feedstore Issue) impacting entire RRM E2E Test Script execution; Blocking PS item # 11597 is impacting Scrap Tracking Report Test Scripts - Dev is investigating on this. * TP21 (the latest round of the Windows Security Update LOB App Compat testing program) is in progress; scheduled to end by 06-June-05 EOD. As per the plan approved by Don & Deva: Test team will update/install the patches on three machines. The testers assigned to those machines will perform their normal set of regression tests. These would be a subset of the entire regression suite as there will not be sufficient time to do all 1500 test cases on the three machines and meet the requirements for SIT* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT & also due to Z18 XBOX Platform execution impacted by blocking issues Yellow
6/6/2005 Test Pass 2 In Progress* Z18 XBOX Platform: PS #11633 Blocking the execution of all 18 test scripts related to 2800 flat file upload.* Z22 Acer SCM B2B Integration: PM is working with eBis on setting up the configuration for 9Z9 processing and setting up of global identifier on 3B2 and 3C1 files. Test will start 9Z9 verification once PM confirms on the configuration. * TP21 (the latest round of the Windows Security Update LOB App Compat testing program) completed successfully; No issues found; Applications Tested: DSS, Orion, CLA, Product Viewer, Entire COA Management, BART * The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT & also due to Z18 XBOX Platform execution impacted by blocking issues Yellow
6/7/2005 Test Pass 2 In Progress* Z18 XBOX Platform: PS #11633 Blocking the execution of all 18 test scripts related to 2800 flat file upload. PM is working with eBis team for resolution.* Blocking PS #11639 was impacting execution of entire TV Main functionality related to COA; Bug resolved by RSA at 6 PM IST today* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT & also due to Z18 XBOX Platform execution impacted by blocking issue Yellow
6/8/2005 Test Pass 2 In Progress* Z18 XBOX Platform: Reactivated Resolved Blocking Issue PS #11633 that is impacting execution of 18 test scripts related to 2800 flat file upload. PM to follow-up with eBis team once again for resolution.* Dev will be ready to drop Z16 Rebate Tracking - ESG, Z26C - RMA Enhancements & .Net Connector upgrade for SBC into SIT by tomorrow - Thursday, June 09, 2005 7PM IST* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT & also due to Z18 XBOX Platform execution impacted by blocking issue Yellow
6/9/2005 Test Pass 2 In Progress* Test is blocked with PS Item #11653 (Replication Failure on SIT servers); This is impacting COA Management Regression, Z22 ACER SCM B2B Integration & E2E Regression Test Script Execution; RSA is investigating on this issue* Code will be dropped tonight 8PM IST for Z16 Rebate Tracking - ESG, Z26C - RMA CR & .Net Connector upgrade for SBC & SMTPHost code change* Z18 XBOX Platform: Blocking Issue PS #11633 closed today * Z26B TV Main Optimization: DTP has been signed off of by PM on June 08, 2005. Test cases are yet to be signed off by PM* Z26C RMA CR: DTP sent to PM for review on June 8th 2005; Will send Test cases today to PM for review; Both the activities are 80% completed; For remaining 20%, Test team requires clarifications from PM on outstanding issues. Code will be dropped into SIT today EOD IST. Test will start the BVT and test execution once DTP and Test cases signed off by PM. * Z16 Rebate Tracking - In ESG: Code will be dropped into SIT today EOD IST. PM communicated to Test that there will be changes to FS. FS, Detailed Test Plan and Test Cases are already signed off. Test needs to get the updated FS for modifying the Detailed Test Plan & Test Scripts. After modification they will be sent to PM for sign off.* Z22 ACER SCM B2B Integration MOO: PS# 11608 and PS#11647 have been reactivated today. These are impacting the complete testing of 9Z9 functionality. A decision will be made on removing 9Z9 functionality from the scope of SIT on 6/10 (Tomorrow).* G3 Effective Dated Pricing: As per the discussion with business, Price override CR will be rolled back (PS #11655). This will be dropped along with the code drop at the end of Test Pass 2 (6/13).* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT, Z16 is undergoing FS changes and also due to blocking issue PS #11633 Yellow
6/10/2005 Test Pass 2 - In Progress; Test plans to work tomorrow Saturday, June 11, 2005 to make progress* Z22 ACER SCM B2B Integration: Test is blocked with PS Item # 11647 (E8002 events are not flown to the ICE Database from eBis). Test processed 34 9Z9 files of Acer to eBis today. These 9Z9s will be processed by eBis team today morning PST. Test will review the test status with PM on Monday, June 13, 2005 at 7PM IST; PS Item # 11599 is resolved by PM as won’t fix with comments “due to ebis sit environemtn issues, the new duns number for acer will not be functional during our SIT runs. no impact on any test cases”. A new bug will be opened in UAT if we see this issue again* Z26C RMA CR: Detailed Test Plan & Test Scripts are sent to PM for review & signoff. As per PM, the change 7 functionality (Enhanced Rejection Reasons) will not be tested for now.* Z16 Rebate Tracking - In ESG: Test is blocked with three PS Items; PS Items # 11659 & # 11666 are resolved now; Waiting for PS Item # 11665 to be resolved to take a drop on all three PS Items; PM to send the updated FS with new changes (Target today EOD PST; PS Item # 11658)* Z26B TV Main Optimization: Signoff received for Test Scripts on 6/10 Morning IST except for few that need to be updated with PM’s review comments.* Blocking Issue PS Item #11653 (Replication Failure on SIT servers) resolved and closed today* The status is yellow as Z16 Rebate Tracking - In ESG and Z26C RMA CR are being dropped late into SIT, Z16 is undergoing FS changes and also due to Z16 blocking issues Yellow
6/13/2005 Test Pass 2 completed today; Test Pass 3 starts tomorrow Tuesday, June 14, 2005 as planned* Z26B TV Main Optimization: Status is yellow; PS Item # 11595 is slowing down the progress on test script execution; project to continue for two more days in Test Pass 2; XML files required from PM for five Xbox events (51 test scripts are impacted); Clarification required on 11 test scripts related to re-written TV Rules for COA; Clarification required on PS Item # 11690 (47 test scripts related to re-written TV Rules for Xbox are impacted)* Z18 XBOX Platform: Status is yellow; the test team could not test the core functionality with respect to Xenon shipments and returns because of blocking bugs (11596, 11621, 11578, 11562, and 11633) during Pass 1 & 2; 8 Test Scripts are impacted by active Sev-2 PS Item # 11676. * Z16 Rebate Tracking - In ESG: Status is yellow; Test is unable to progress due to PS Issues & Pending FS updates; PM to discuss with Dev and update FS; Based on this, Test will make test scripts modification & continue testing* Z26C RMA CR: Status is yellow; waiting for the clarification from PM on “Total COAs on RMA” field value calculation. Four test scripts are dependent on this; One Sev-2 PS Item is still active (PS# 11663); project to continue for one more day in Test Pass 2 to complete testing* Z22 ACER SCM B2B Integration: Status is green; Pass 2 completed successfully* G3 NonSAP Effect Dated Pricing: Status is green; Pass 2 completed successfully* K7 - DSS Disti CLA Improvements: Status is green; Pass 2 completed successfully* AQR Regression: Status is green; Pass 2 completed successfully; Active PS Item # 11595 impacted the progress on TVMain related regression test scripts. Yellow
6/14/2005 Test Pass 3 started today* Z26B TV Main Optimization: Status is yellow; Test Pass 2 In Progress and will end tomorrow; Received XML files from PM for all events requested except for 1; Resolved blocking PS Item # 11690 impacting functionality related to Re-Written TV Rules for Xbox (48 Test Cases); This is currently assigned to moostdrp* Z18 XBOX Platform: Status is yellow; Active PS #11676 is blocking 8 test cases related to 2800 flat file upload. Active PS #11696 and resolved PS #11700 impacting execution of 11 reshipment E2E scenarios.* Z16 Rebate Tracking - In ESG: Status is yellow; Test is unable to progress due to PS Issues & Pending FS updates; PM to discuss with Dev and update FS (target 6/14 EOD PST); Based on this, Test will make test scripts modification & continue testing; Contingency plan has been discussed and posted in AQR RTP folder on SharePoint.* Z26C RMA CR: Status is yellow; Test Pass 2 completed today; Test Pass 3 will start tomorrow; Test will be completely blocked till resolved PS # 11700 is dropped into SIT; PS # 11700 is currently assigned to moostdrp* Z22 ACER SCM B2B Integration: Status is green; Test is blocked till resolved PS # 11700 is dropped into SIT* G3 NonSAP Effect Dated Pricing: Status is green; Pass 3 In Progress* K7 - DSS Disti CLA Improvements: Status is green; Pass 3 completed successfully* AQR Regression: Status is green; Pass 3 In Progress; ~ 35 E2E regression test scripts are blocked with resolved PS # 11700 Yellow
6/15/2005 Test Pass 3 In Progress* Z26B TV Main Optimization: Status is yellow; Test Pass 2 completed today; Test Pass 3 will start tomorrow; Resolved blocking PS Item # 11690 dropped today into SIT. Test Team is waiting for XML file for Xbox event 2600 from PM (impacting execution of 3 Test Scripts) – PS Item # 11697.* Z18 XBOX Platform: Status is yellow; Test Pass 3 In Progress; Active PS #11676 is blocking 8 test cases related to 2800 flat file upload. PM is working with eBis team for resolution (Target 6/16); PS # 11706 was blocking 11 E2E’s related to RMA returns and 15 Xbox E2E’s Regression Scripts (Resolved now at 7PM IST); Reactivated PS Item #11696 – Impacting 3 Regression test cases with respect to Xbox Returns* Z16 Rebate Tracking - In ESG: Status is yellow; Test is completely blocked with PS Item # 11658 for FS updates (Target Completion Date is 6/17)* Z26C RMA CR: Status is yellow; Test Pass 3 started today; Blocking PS Item # 11706 resolved today at 7 PM IST* Z22 ACER SCM B2B Integration: Status is green; Blocking PS Item # 11706 resolved today at 7 PM IST* G3 NonSAP Effect Dated Pricing: Status is green; Test Pass 3 In Progress* K7 - DSS Disti CLA Improvements: Status is green; Pass 3 completed successfully * AQR Regression: Status is green; Pass 3 In Progress; Active Blocking PS item # 11707 impacting execution of 100% of E2E regression test scripts. RSA raised ticket with eBis (SR# 2-415855635) on this. Blocking PS item # 11702 related to digital certificate retirement resolved today. Currently assigned to Yukako for further action. Yellow
6/16/2005 Test Pass 3 In Progress* Z26B TV Main Optimization: Status is yellow; Test Pass 3 started today; Test Team is waiting for XML file for Xbox event 2600 from PM (impacting execution of 3 Test Scripts) – PS Item # 11697; Currently ArchivingData job is run in batches instead of running continuously - PM to get back on the SIT Sign-Off criteria for this job – PS Item #11638* Z18 XBOX Platform: Status is yellow; Active PS #11676 is blocking 8 test cases related to 2800 flat file upload. PM is working with eBis team for resolution (Target 6/17); Reactivated PS Item #11696 – Impacting 3 Regression test cases with respect to Xbox Returns (Target Resolution - 6/17)* Z16 Rebate Tracking - In ESG: Status is Red; Test is completely blocked with PS Item # 11658 for FS updates (Target Completion Date - 6/17); PM to finalize on field validations – PS Item # 11678 (Target – 6/21); Test will modify Test Scripts after receiving the updated FS (including field validations); Test will resume test execution after receiving signoff on modified test scripts.* Z26C RMA CR: Status is yellow; expecting good progress tomorrow as the Blocking issues are resolved now* Z22 ACER SCM B2B Integration: Status is green; expecting good progress tomorrow as the Blocking issues are resolved now* G3 NonSAP Effect Dated Pricing: Status is green; * K7 - DSS Disti CLA Improvements: Status is green; Pass 3 completed successfully * AQR Regression: Status is green; Blocking PS item # 11707 resolved today. Testing on digital certificate retirement will start from tomorrow – 6/17 Yellow
6/17/2005 Test Pass 3 In Progress* Z26B TV Main Optimization: Status is yellow; Test Pass 3 started today; Test Team is waiting for XML file for Xbox event 2600 from PM (impacting execution of 3 Test Scripts) – PS Item # 11697; Currently ArchivingData job is run in batches instead of running continuously - PM to get back on the SIT Sign-Off criteria for this job – PS Item #11638.* Z18 XBOX Platform: Status is yellow; PS #11676 is blocking 8 test cases related to 2800 flat file upload has been assigned to test team. Test team requires clarification from PM on this.* Z16 Rebate Tracking - In ESG: Status is Red; RTP Z16 Test Team is proceeding with using the current test cases to test the application. The test cases are stated as being blocked due to required FS changes which will cause required modifications to the test case suite. The results will be logged once the FS has been changed and the appropriate changes made to the test cases(PS Item #11658 for FS updates); As per the latest update from PM, "The latest FS v6.16 is posted but is not yet final as I am waiting for additional details from Mike on the workflow documents soon to be attached in appendix F of the FS." * Z26C RMA CR: Status is Green; Test Pass 2 is in progress.* Z22 ACER SCM B2B Integration: Status is green; Test case execution is in progress.* G3 Non SAP Effect Dated Pricing: Status is green.* K7 - DSS Disti CLA Improvements: Status is green.* AQR Regression: Status is green; Test team was blocked due to PS#11721: Invoice correction update procedure was blocking all the processes on COADB for over one hour; This has been resolved by RSA and testing is back on track.* Digital Certificate Retirement: Status is Green; Testing on digital certificate retirement has begun, no issues found so far. This will be covered as part of test case execution for Test Pass 3; Test team is only going to execute remaining unexecuted test cases for test pass 3 and test cases that have been passed for test pass 3 (Apprpox ~560) before the commencing of Digital Certificate Retirement test execution will be marked as failed. Yellow
6/20/2005 Test Pass 3 In Progress* Z26B TV Main Optimization: Status is yellow; Test team is awaiting XML file for Xbox event 2600 from PM (impacting execution of 3 test scripts) - PS Item # 11697; Currently ArchivingData job is run in batches instead of running continuously - PM to get back on the SIT sign-off criteria for this job. Running of ArchivingData job is slowing down events from getting processed from EventStage - PS Item # 11638; XBox related Events are not processed from EventStage - PS item # 11595, this is blocking the execution of entire TVMainforXBox functionality - 45 test scripts in all.* Z22 ACER SCM B2B Integration: Status is green; awaiting 9z9 processing by eBis during PST today.* Z26C RMA CR: Status is yellow; awaiting resolution of PS item # 11705* G3 NonSAP Effect Dated Pricing: Status is green* K7 - DSS Disti CLA Improvements: Status is green; Pass 3 completed successfully * Z16 Rebate Tracking - In ESG: Status is Red; Contingency plans are being discussed throughout the day. A further update to follow.* Z18 XBOX Platform: Status is yellow; Active PS # 11676 is blocking 9 test cases related to 2800 flat file upload. PM to work with eBis team for resolution during PST today. These test scripts could not be tested so far; Active PS item # 11737 is also related to eBis, currently assigned to Bhavnesh for follow-up; PS item # 11670 has been made dependent on production bug 11650 and is awaiting resolution.* AQR Regression: Status is green; Active PS item # 11707 is affecting the execution of 6 E2E regression scripts at this stage; currently assigned to Bhavnesh for follow-up with eBis. Yellow
6/21/2005 Test Pass 3 In-Progress* Z16 Rebate Tracking - In ESG: Status is Red; Contingency plans have been discussed last night IST. A further update to follow.* Z18 XBOX Platform: Status is Yellow; Active PS # 11676 which was resolved last night IST has been reactivated again today morning i.e. 06/21, it is blocking 2 test cases related to 2800 flat file upload. This has been discussed with PM in the call tonight.* Z26C RMA CR: Status is Yellow; PS Item # 11705 which was dropped last night has been reactivated today and new PS#11750 has been logged today. * Z26B TV Main Optimization: Status is Yellow. Test team has received Xbox E2600 xml file from PM and related PS Item # 11697 has been resolved and closed; PS Item # 11638: Running of ArchivingData job which was slowing down processing at COADB resolution has been postponed and it is out of scope for the project with 2 test cases related to this functionality removed from scope. Blocking bug PS# 11595 has been resolved today. As blocking issues are resolved, test team is making good progress on test execution. * G3 Non SAP Effect Dated Pricing: Status is Green. Test Pass 3 successfully completed.* K7 - DSS Disti CLA Improvements: Status is Green. Test Pass 3 successfully completed.* Z22 ACER SCM B2B Integration: Status is Green. Test Pass 3 successfully completed.* AQR Regression: Status is Green; Test Pass 3 is in progress.* Digital Certification Retirement: Status is Green; Test Pass 3 is in progress. As the digital certificates were not removed in a timely enough fashion 621 regression test cases will not be part of the digital certificate removal project at this point. Yellow
6/22/2005 Test Pass 3 In-Progress* Z16 Rebate Tracking - In ESG: Status is Red; Contingency plans have been discussed. Received updated FS ver 6.17 from PM. Updated FS is expected to be signed off by Business, T2, Test and the PM groups (Target 6/27).* Z26B TV Main Optimization: Status is Yellow. PS#11749 is assigned to Yukako (PM) for resolution. Test cases related to XBOX - checking for App Type as 1 need to be clarified from PM and updated accordingly. Test will discuss with PM tomorrow (6/23) morning IST on this.* Z18 XBOX Platform: Status is Yellow; Active PS # 11676 impacting 1 negative test case - currently assigned to PM. As per PM, “Mike is looking into this and will provide an update”. One test case is blocked as the OEMDM_Factory is not publishing to OEMDM_Redmond; Bill Carswell is looking into this issue.* Z26C RMA CR: Status is Green. Test Pass 3 successfully completed. * G3 Non SAP Effect Dated Pricing: Status is Green. Test Pass 3 successfully completed.* K7 - DSS Disti CLA Improvements: Status is Green. Test Pass 3 successfully completed.* Z22 ACER SCM B2B Integration: Status is Green. Test Pass 3 successfully completed.* AQR Regression: Status is Green; Test Pass 3 is in progress.* Digital Certification Retirement: Status is Green; Test Pass 3 is in progress. Yellow
6/23/2005 Test Pass 3 In-Progress; will be completed by tomorrow (6/24) as planned; SIT Sign-off meeting scheduled on next Monday (6/27)* Z16 Rebate Tracking - In ESG: Status is Yellow; Contingency plans have been discussed. Z16 to continue in SIT for two more weeks; The updated FS is waiting to be signed-off by Business, T2, Test and the PM groups (Target 6/27)* Z26B TV Main Optimization: Status is Yellow; Resolved PS Item #11768 is blocking execution of re-written TV Rules for XBOX (14 test scripts) - Awaiting PM’s clarification. * Z18 XBOX Platform: Status is Yellow; Resolved Sev-2 PS #11676 is dropped into SIT today – Reactivated after regression. Currently assigned to Mike Adams; Active Sev-2 PS #11769 is assigned to Shivani for follow-up* Z26C RMA CR: Status is Green. Test Pass 3 successfully completed. * G3 Non SAP Effect Dated Pricing: Status is Green. Test Pass 3 successfully completed.* K7 - DSS Disti CLA Improvements: Status is Green. Test Pass 3 successfully completed.* Z22 ACER SCM B2B Integration: Status is Green. Test Pass 3 successfully completed.* AQR Regression: Status is Green; Test Pass 3 successfully completed.* Digital Certification Retirement: Status is Green; Testing in SIT completed. No issues found on the test scripts executed; Testing in UAT In-Progress Yellow
6/24/2005 Test Pass 3 successfully completed; SIT Sign-off meeting scheduled on next Monday (6/27) 8 PM IST* Z16 Rebate Tracking - In ESG: Status is Yellow; Contingency plans have been discussed. Z16 to continue in SIT for two more weeks; the updated FS is waiting to be signed-off by Business, T2, Test and the PM groups (Target 6/27) * Z26B TV Main Optimization: Status is Green; Test Pass 3 successfully completed; Active TV Main regression Sev-2 PS Item #11773 to be resolved tonight IST by Dev; Test to regress tomorrow, Saturday 6/25 IST after the code drop.* Z18 XBOX Platform: Status is Green; Test Pass 3 successfully completed* Z26C RMA CR: Status is Green. Test Pass 3 successfully completed* G3 Non SAP Effect Dated Pricing: Status is Green. Test Pass 3 successfully completed* K7 - DSS Disti CLA Improvements: Status is Green. Test Pass 3 successfully completed* Z22 ACER SCM B2B Integration: Status is Green. Test Pass 3 successfully completed* AQR Regression: Status is Green; Test Pass 3 successfully completed* Digital Certification Retirement: Status is Green; Testing in SIT & UAT successfully completed Green